SUBMITTED BY ARTHUR N1ORC - AMSAT A/C #31468
May 12, 2006
Katherine Trinidad
Headquarters, Washington
(202) 358-3749
Jessica Rye
Kennedy Space Center, Fla.
(321) 867-2468
STATUS REPORT: S06-016
NASA'S SPACE SHUTTLE PROCESSING STATUS REPORT: S06-016
NASA's space shuttle fleet is housed and processed at Kennedy Space
Center, Fla.
Mission: STS-121 - 18th ISS Flight (ULF1.1) - Multi-Purpose Logistics
Module
Vehicle: Discovery (OV-103)
Location: Vehicle Assembly Building
Launch Date: Launch Planning Window July 1-19, 2006 Launch Pad: 39B
Crew: Lindsey, Kelly, Sellers, Fossum, Nowak, Wilson and Reiter
Inclination/Orbit Altitude: 51.6 degrees/122 nautical miles
Discovery was moved today from Orbiter Processing Facility Bay 3 to
the Vehicle Assembly Building, a major step toward a launch to the
International Space Station. Technicians and crane operators began
preparations to lift Discovery into the assembly building's High Bay
3 and attach the shuttle to its external fuel tank and twin solid
rocket boosters. After final integration, a crawler transporter is
scheduled to carry Discovery to the launch pad May 19.
Discovery was scheduled to move Thursday, but a sheared left-hand jack
screw on the lifting sling in the assembly building postponed the
rollover until today. Both the right and left-hand screws were
removed and replaced. The replacements were inspected, analyzed,
proof loaded and installed on the sling.
The payloads that will launch aboard Discovery were loaded into the
payload transportation canister this week and are scheduled to roll
out to the launch pad on May 16. Discovery's payloads include the
Italian-built logistics module, known as Leonardo, which will carry
food, clothing, spare parts and research equipment to the station.
Other payloads include two cargo carriers which contain heat shield
tile samples, a spare pump module and a replacement mobile
transporter reel assembly.
For previous space shuttle processing status reports, visit:
http://www.nasa.gov/shuttle
-end-
----